Boston Landmarks Commission Hearing 2/27/2018
The commission will hold its monthly public design review hearing on Tuesday, February 27, 2018.
USE CONGRESS STREET AS AN ENTRANCE/EXIT AFTER 5:30 P.M.
Discussion Topics
-
Design Review - 4:30 PM
18.606.42 Franklin Park (William Devine Golf Course)
Applicant: Allison Perlman, Boston Parks and Recreation Department
Proposed work: Installation of a cart boardwalk and landscape alterations at the William Devine Golf Course18.606.42 Franklin Park (Circuit Drive)
Applicant: Chris Cook, Commissioner Boston Parks and Recreation Department
Proposed work: Pathways and entrances improvements near Scarboro Pond, Morton Street, and Circuit Drive18.890.66 Blackstone Block (Blackstone Street Sidewalk)
Applicant: Yvette Tetreault, Haymarket Parcel 9 Investors, LLC
Proposed work: Sidewalk renovation, including replacement of asphalt with concrete, removal and resetting of granite elements -
Administrative Review/Approval
► Applicants whose projects are listed under this heading NEED NOT APPEAR at the hearing. Please see agenda for details. If you have any questions, please contact staff at 617-635-3850 or BLC@boston.gov.
18. 847.BV 18 Fayette Street
Applicant: Anthony Cunagin, AWC Construction, LLC
Proposed work: Replacement of two first floor windows18.875.04 Boston Common Frog Pond
Applicant: John Schaub, General Manager
Proposed work: Temporary installation of carousel and ticket booth between parade ground and Frog Pond18.876.04 Boston Common Brewer Fountain
Applicant: John Schaub, General Manager
Proposed work: Temporary installation of bistro tables and chairs and umbrella at Brewer Fountain18.877.04 Boston Common Frog Pond
Applicant: John Schaub, General Manager
Proposed work: Temporary installation of bistro tables, chairs, and planters at the Frog Pond Pavilion18.809.12 39-6 Commercial Wharf
Applicant: Richard A. Cifuni, Life House Construction
Proposed work: Installation of a balcony18.819.12 59-4 Commercial Wharf
Applicant: Jahn Spagnoli, Apex Carpentry, LLC
Proposed work: Replacement of three windows and one door18.882.26 Federal Reserve Bank
Applicant: Ron H. Pellerine, The Langham
Proposed work: Relocation of two doors such that the revolving door is in the middle of three existing openings18.889.78 72 Broad Street
Applicant: Suzan Adelman, Folio Boston Condominium Trust
Proposed work: Installation of automatic door push plate at the entrance -
Business Hearing - 6:00 PM
1. Discussion and Vote on Design Review Applications
2. Review and ratification of 02/13/2018 meeting minutes3. Demolition Delay Hearing: 1173 Adams Street
Application #18.240D2247
Applicant: Denis Keohane, 177 West Seventh Street Realty Trust
Re: Review of proposed demolition of commercial structure at 1173 Adams Street, Dorchester, MA 021244. Demolition Delay Hearing: 11 Burney Street
Application #18.815D2302
Applicant: Mitch Wilson, New Urban Partners, LLC
Re: Review of proposed demolition of a triple-decker at 11 Burney Street, Boston, MA 021205. Updates
- Projected Adjournment - 8:00 PM