city_hall

Les sites officiels utilisent .boston.gov

Un site .boston.gov appartient à une organisation gouvernementale officielle de la City of Boston.

lock

Les sites .gov sécurisés utilisent HTTPS

Un cadenas ou https:// signifie que vous vous êtes connecté en toute sécurité au site web .gov. Ne partagez des informations sensibles que sur des sites web officiels et sécurisés.

Boston.gov Search

Get direct answers to your questions about City of Boston services, programs, and information. While we strive for accuracy by sourcing directly from Boston.gov, our search can occasionally provide unexpected results. You can help us improve by using the feedback buttons below each answer.

Des questions ? Contactez-nous à digital@boston.gov.

Choisissez un type de recherche

William Felton 'Bill' Russell Bridge

Public Works is designing a replacement for the bridge in Charlestown. MassDOT will construct the new bridge.

Vous avez des questions ? Contactez:

Phase du projet

timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
Pending
Planning
Design
Construction
Complete

Informations sur le projet

Location
North Washington Street Bridge Charlestown 02129
See all
Année de réalisation
2025
Primary Project Type
Streets

The new bridge will complement the Zakim Bunker Hill Bridge next door. The new bridge will be walkable, multi-modal, green, and sustainable. Everyone will be able to safely use the bridge. That includes pedestrians, cyclists, and motorists.

The design calls for:
  • wider sidewalks
  • gathering places
  • innovative accent lighting
  • protected bicycle facilities, and
  • smoother walking surfaces to support the Freedom Trail.

Timeline

Timeline
  • July 16, 2017: Plan Specification and Estimate Submission (Final)
  • September 16, 2017: Advertised for Bidding
  • February 27, 2018: Bids Opened
  • August 18, 2018: “Notice to Proceed” Provided to JW White
  • 2019/2020: Temporary bridge constructed
  • July 18, 2020: Traffic switched to temporary bridge
  • December 9, 2023: Traffic switched to permanent bridge
  • October 21, 2024: Ceremony celebrating the Bridge Renamed William Felton “Bill” Russell Bridge
  • Summer 2025: Anticipate all lanes on permanent bridge to be open