Project Name
Washington Street Urban Wild
Project Parcels
Neighborhood
DORCHESTER
Councilor
Worrell
Property Size
32,074 sq/ft
Developer
Urban Guild Inc.
Project Goals
These four parcels have been sold to The Guild for preservation as an urban forest. Construction is expected to begin in summer 2024 on forest improvements.
Timeline
Winter 2020
Community Feedback
Community Feedback
We’re meeting with community members to gather feedback on plans for the site.
Nov 27 2020
A community meeting will be held in partnership with Mt Bowdoin Betterment Association on Saturday, December 19. Further details will be posted on this page soon.
Campbell Stras
| Project Manager
Dec 03 2020
DND will be gathering feedback on the proposed use of these parcels as a permanent urban wild at the Mt. Bowdoin Betterment Association's December monthly virtual meeting, to be held at 10:30 AM on Saturday, December 19. Please see below for meeting details. Join Zoom Meeting https://fayerweather.zoom.us/j/95000735725?pwd=OHArVlM5NklDZWpPN3NtMmo0OW9pQT09 Meeting ID: 950 0073 5725 Passcode: 055339 One tap mobile +12063379723,,95000735725# US (Seattle) Dial by your location +1 206 337 9723 US (Seattle) Meeting ID: 950 0073 5725 Find your local number: https://fayerweather.zoom.us/u/aAmWk0h4S
Campbell Stras
| Project Manager
Jan 12 2021
Thanks to everyone who was able to make it to the Mt. Bowdoin Betterment Association meeting on December 19, at which DND solicited feedback on the proposed use of these parcels. A video recording of the meeting can be found below. MBBA Meeting 12/19 Support for the use of these parcels as preserved open space was strong, and DND plans to issue a Request for Proposals in February 2021.
Shani Fletcher
| Project Manager
Fall 2021
Developer Selection
Developer Selection
We’ll release a Request for Proposals and select a developer for this site.
Sep 27, 2021
Request for Proposals (RFP) Opened for Bidding
Summer 2022
City Planning
City Planning
We're working with the developer on the final design, budget, and financing.
Aug 19 2022
The Public Facilities Commission voted to approve the tentative developer designation of Urban Guild, Inc. for these parcels in the meeting on August 17, 2022. See below for the full proposal.
Theresa Strachila
| Project Manager
Spring 2024
Under Construction
Under Construction
Construction is underway. For further information on road closures and parking impact, contact the Project Manager.
Project Complete
Project Complete
Predicted Date: Fall 2024