CITY OF BOSTON

PUBLIC FACILITIES DEPARTMENT (PFD)

Request for Qualifications (RFQ)

Moon Island Seawall

43 Moon Island Road, Quincy, MA

Project No. 7222

Contact Information

PFD Bid Counter

Bid.info@boston.gov

(617) 635-4809

Pursuant to Massachusetts General Laws Chapter 7C, §§ 44-57, the City of Boston’s Public Facilities Department (PFD) is requesting qualification statements for design services including Schematic Plans and Outline Specifications; Design Development Plans and Specification; Construction Plans and Specifications; Administration of Construction Contract; and Construction Supervision for the Moon Island Seawall project.

The scope of services for the Moon Island Seawall project consists of chosen firm to recommend and design procedures for stabilization and repair of seawall on Moon Island.  Candidates must show expertise in coastal engineering and resiliency consulting as well as geotechnical engineering services.

Project fees will follow the schedule as stated in the application form. Completion shall be 104 weeks after execution of a contract. Applicants must be a registered Engineer in the Commonwealth of Massachusetts.

A program for this project will not be prepared beyond the scope of services stated above.

The project will be performed under applicable M.G.L. c.30, §39M.

Applicants must provide the names of key personnel and consultants that will be utilized on this project for the following disciplines: Civil and Geotechnical Engineer, Code and Geoenvironmental Consultant, Specifications Writer and Cost Estimator.

Applicants, at a minimum, must have prior experience on the following types of projects the design, building and maintenance of coastal structures, coastal engineers are often interdisciplinary involved in integrated coastal zone management; this may include providing input and technology for e.g. environmental impact assessment.

The Designer Application Package will be available on September 21, 2020 at the Public Facilities Department Bid Counter to all interested parties.  The Designer Application Packages are only available electronically and by requesting access for such through bid.info@boston.gov.   Statements of Qualifications must be submitted in sealed envelopes and returned to PFD Bid Counter, 26 Court Street, 1st Floor, Boston, Massachusetts 02108 by October 14, 2020 no later than 2:00 P.M.  LATE QUALIFICATION STATEMENTS WILL NOT BE ACCEPTED.

Applicants are hereby notified a site viewing is scheduled for Wednesday, September 30, 2020, at 10 a.m. SHARP at the Guard Shack, 43 Moon Island Road, Quincy, MA.

Corona COVID-19 Precaution notice: Anyone attending site viewing(s) will be required to follow state and city precaution guidelines by wearing the necessary face mask and practicing safe distancing. 

Patrick I. Brophy, Chief of Operations