Construction hours: 7:00 a.m. to 3:30 p.m.

Below is a summary of the primary construction activities for the next few weeks. This schedule is subject to change based on weather conditions and other factors.

Planned work  7/7 - 7/11
  • Forming and installing sidewalks from Hebron St. to Livermore S.
  • Installing curb and pedestrian ramps around the Greenfield/ Weybosset Area
  • Continue placing recessed planter soil between Wood Ave and Weybosset St
Planned work 7/14 - 7/18
  • Installing curb from Hebron St to Livermore St
  • Installing curb and pedestrian ramps around the Weybosset Corner towards Livermore St
  • Installing rotary island curb and concrete
Planned work 7/21 - 7/25
  • Forming and installing sidewalks from Livermore St to Weybosset St
  • Installing curb from Livermore St to Weybosset St
  • Finishing rotary island curb and concrete

     