Planned work 7/7 - 7/11
- Forming and installing sidewalks from Hebron St. to Livermore S.
- Installing curb and pedestrian ramps around the Greenfield/ Weybosset Area
- Continue placing recessed planter soil between Wood Ave and Weybosset St
Planned work 7/14 - 7/18
- Installing curb from Hebron St to Livermore St
- Installing curb and pedestrian ramps around the Weybosset Corner towards Livermore St
- Installing rotary island curb and concrete
Planned work 7/21 - 7/25
- Forming and installing sidewalks from Livermore St to Weybosset St
- Installing curb from Livermore St to Weybosset St
- Finishing rotary island curb and concrete