city_hall

Official websites use .boston.gov

A .boston.gov website belongs to an official government organization in the City of Boston.

lock

Secure .gov websites use HTTPS

A lock or https:// means you've safely connected to the .gov website. Share sensitive information only on official, secure websites.

< Go to Building Housing Homepage
Project Name

Parker Street Development

Project Parcels

1000495000

725 PARKER ST
Owner:
Other
3,207sqft

1000496000

729 R PARKER ST
Owner:
Other
2,473sqft
Project Images
Neighborhood
Jamaica Plain
Councilor
Durkan
Units Total
Two
Income-Restricted Units
Two
Property Size
5,680 sq/ft

Developer

Habitat for Humanity Greater Boston, Inc.

Project Goals

DND has tentatively designated Habitat for Humanity to develop these vacant land parcels. Working jointly with the local community, and after productive community meetings to define use, development and design objectives, DND issued a Request for Proposal for two vacant, city-owned Mission Hill parcels on March 17, 2017. These parcels, 725-727 Parker Street and 729 R Parker Street, are designated for the purpose of constructing two affordable housing units. Proposals for this project were received on April 28, 2017. DND held a community meeting on June 27 for eligible applicants to present their proposals, as part of DND's application review process, and prior to DND recommending developers for each site. Developer PowerPoint presentations from the June 27th meeting are included in DND's public website for review and comment. The project is slated to include 2 home ownership units. These 2 units will be offered as affordable housing and will include the following bedroom mix: (2) four bedroom units.

Timeline

Winter 2016

Community Feedback

We’re meeting with community members to gather feedback on plans for the site.

Spring 2017

Developer Selection

We’ll release a Request for Proposals and select a developer for this site.

Mar 17, 2017

Request for Proposals (RFP) Opened for Bidding

Winter 2017

City Planning

This project is going through a zoning review with the Boston Planning and Development Agency (BPDA). Then we’ll work with the Developer on funding, design, and compliance.

Fall 2019

Under Construction

Construction is underway. For further information on road closures and parking impact, contact the Project Manager.

Project Complete

Predicted Date: To Be Determined