Project Name

273 Highland aka Highland/Marcella Package 4

Project Parcels

Click for project details

283 HIGHLAND ST
Owner:
City of Boston - DND
1,640sqft

Click for project details

277 Highland ST
Owner:
City of Boston - DND
1,592sqft

Click for project details

281 281A HIGHLAND ST
Owner:
City of Boston - DND
1,629sqft

Click for project details

275 HIGHLAND ST
Owner:
City of Boston - DND
1,592sqft

Click for project details

279 HIGHLAND ST
Owner:
City of Boston - DND
1,708sqft

Click for project details

273 HIGHLAND ST
Owner:
City of Boston - DND
3,747sqft

Click for project details

287 Highland ST
Owner:
City of Boston - DND
4,446sqft

No photos uploaded (yet!)

Neighborhood
Roxbury
Councilor
Fernandes Anderson
Units Total
23
Income-Restricted Units
23
Property Size
16,354 sq/ft

Developer

Rees-Larkin Development LLC

Project Goals

In January, 2018 MOH issued an RFP for five Development Packages comprised of 33 parcels on Marcella and Highland Streets. The guidelines established in the 2018 RFP reflected extensive collaboration with the Highland Park Project Review Committee and the BPDA to establish preferred and acceptable uses and outline Energy Positive (E+) design guidelines.
After review of proposals received, in October 2018 MOH recommended and the Public Facilities Commission approved the developer designation of Rees-Larkin Development. Rees-Larkin Development will construct 23 new cooperative housing units. There will be 19 parking spaces below grade. All units will be affordable at 60% AMI or below. The development will be energy positive, LEED "Platinum" and will include communal gallery space, and open space.

Timeline

Community Feedback

We’re meeting with community members to gather feedback on plans for the site.

Fall 2017

Developer Selection

We’ll release a Request for Proposals and select a developer for this site.

Nov 13, 2017

Request for Proposals (RFP) Opened for Bidding

Fall 2018

City Planning

This project is going through a zoning review with the Boston Planning and Development Agency (BPDA). Then we’ll work with the Developer on funding, design, and compliance.

Winter 2025

Under Construction

Construction is underway. For further information on road closures and parking impact, contact the Project Manager.

Project Complete

Predicted Date: Summer 2026